| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIST-04 | ELABORACON DE PRETIL EN HUECO PASO DE HOMBRE CON SECCION DE 15 x 20 CMS. A BASE DE CONCRETO F¨C=200 kg/cm2, INCLUYE : ANCLAJE CIMBRADO DECIMBRADO,MANO DE OBRA,MATERIALES, LIMPIEZA Y TODO LONECESARIO PARA SU CORRECTA EJECUCION. | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.002384 | $10,450.00 | $24.91 |
| CHE-ACERO-REFUER-05 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | TON | 0.000750 | $12,000.00 | $9.00 |
| CHE-ACERO-REFUER-06 | ALAMBRE RECOCIDO NO. 18 | KG | 0.150000 | $13.82 | $2.07 |
| Suma de Material | $35.99 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.040331 | $1,006.54 | $40.59 |
| Suma de Mano de Obra | $40.59 | ||||
| Auxiliar | |||||
| CHE-CONCRETO200 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.030900 | $1,213.47 | $37.50 |
| CIM0009 | Cimbra comun cadenas, castillos, cejas repisones seccion mayor a 0.020m2 incluye: materiales y mano de obra. | m2 | 0.400000 | $116.86 | $46.74 |
| Suma de Auxiliar | $84.24 | ||||
| Costo Directo | $160.82 |