| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIST-10 | ELABORACION DE CARCAMO CON DIMENCIONES DE 3.40 x 0.50 m. A BASE DE CONCRETO PREMEZCLADO COLADO MONOLITICAMENTE INCLUYE CIMBRA, ACERO,CONCRETO Y TODO LONECESARIO PARA SU CORRECTA EJECUCION. | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-ACERO-REFUER-02 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | TON | 0.032000 | $10,450.00 | $334.40 |
| CHE-CONCRETO-01 | CONCRETO PREMEZC.RR F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | M3 | 1.700000 | $985.72 | $1,675.72 |
| CHE-CIMBRA-04 | Barrote 2" x 4" x 8' | pt | 2.500000 | $9.36 | $23.40 |
| CHE-CIMBRA-051 | Polin 4" x 4" X 8´ | pt | 3.800000 | $6.37 | $24.21 |
| CHE-CIMBRA-033 | Duela 1" x 4" x 8' | pt | 4.200000 | $11.40 | $47.88 |
| CHE-CIMBRA-07 | CIMBRAPLAY DE PINO DE 16 MM 1 CARA | HOJA | 1.050000 | $310.00 | $325.50 |
| CHE-CIMBRA-02 | CLAVO DE 2 1/2" A 3 1/2" | KG | 1.500000 | $16.55 | $24.83 |
| CHE-COMBUST-01 | COMBUSTIBLE DIESEL | LT | 2.000000 | $8.32 | $16.64 |
| Suma de Material | $2,472.58 | ||||
| Mano de Obra | |||||
| CUA-CHE-03 | CUADRILLA ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.500000 | $1,006.54 | $503.27 |
| CUA-CHE-04 | CUADRILLA ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE ) | JOR | 1.500000 | $1,082.45 | $1,623.68 |
| CUA-CHE-01 | CUADRILLA ( 1 PEON ) | JOR | 0.500000 | $449.42 | $224.71 |
| Suma de Mano de Obra | $2,351.66 | ||||
| Equipo | |||||
| CHE-EQUIPO-034 | Esmeriladora | HR | 4.000000 | $2.88 | $11.52 |
| Suma de Equipo | $11.52 | ||||
| Auxiliar | |||||
| MEZMOR 1:4 | MEZCLA MORTERO CEM-ARENA 1:4 | M3 | 0.068000 | $1,204.38 | $81.90 |
| Suma de Auxiliar | $81.90 | ||||
| Costo Directo | $4,917.65 |