| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| I.3 | SUMINISTRO, HABILITADO, FABRICACIÓN Y MONTAJE DE ESTRUCTURA METÁLICA A BASE DE VIGA IR Y PLACA A-36; INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO. UNA MANO DE PRIMARIO ANTICORROSIVO TALLER. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IR DIF. MEDIDAS | IR DIF. MEDIDAS | KG | 1.020000 | $13.40 | $13.67 |
| PLACA A-36 | PLACA A-36 | KG | 0.050000 | $13.35 | $0.67 |
| GAS P/ CORTES | GAS P/ CORTES | KG | 0.007000 | $8.70 | $0.06 |
| OXIGENO | OXIGENO | M3 | 0.010000 | $19.00 | $0.19 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.023000 | $35.00 | $0.81 |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002000 | $45.00 | $0.09 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.005000 | $0.00 | $0.00 |
| Suma de Material | $15.48 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.002000 | $711.63 | $1.42 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.002000 | $711.63 | $1.42 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.002000 | $1,363.22 | $2.73 |
| Suma de Mano de Obra | $5.57 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | Equipo de corte de oxi-butano | HR | 0.012000 | $9.56 | $0.11 |
| ESMERILADORA | Esmeriladora | HR | 0.020000 | $2.88 | $0.06 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.010000 | $12.48 | $0.12 |
| GRUA | Grua de 20 ton. | HR | 0.002000 | $378.31 | $0.76 |
| Suma de Equipo | $1.05 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 0.020000 | $36.96 | $0.74 |
| Suma de Auxiliar | $0.74 | ||||
| Costo Directo | $22.85 |