| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERR-41 | SUMINISTRO Y COLOCACION DE BASE PARA EQUIPO DE REFRIGUERACION COLOCADO SOBRE LOSA DE EQUIPO DE REFRIGUERACION INCLUYE MATERIALES Y MANO DE OBRA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-MOTO-PTR-01 | PTR DE DIFERENTES MEDIDAS | KG | 1,000.000000 | $16.00 | $16,000.00 |
| CHE-ESTRUC-16 | PLACA DE ACERO A-36 DE 3/16" | kg | 100.000000 | $13.59 | $1,359.00 |
| CHE-TAQUETE HILT-3/8 | TAQUETES HILTI DE 3/8 | PZA | 20.000000 | $20.00 | $400.00 |
| CHE-COMBUST-06 | GAS MARCA VERAGAS | KG | 70.000000 | $8.70 | $609.00 |
| CHE-COMBUST-05 | OXIGENO | M3 | 70.000000 | $52.00 | $3,640.00 |
| CHE-ESTRUC-01 | SOLDADURA E-7018 DE 1/8" | KG | 30.000000 | $52.00 | $1,560.00 |
| CHE-ESTRUCMET-13 | DISCO ABRASIVO | PZA | 10.000000 | $45.00 | $450.00 |
| CHE-FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.500000 | $0.00 | $0.00 |
| Suma de Material | $24,018.00 | ||||
| Mano de Obra | |||||
| CUA-CUADRILLA NO-10 | Cuadrilla de 1 of.pailero + 1 ayudante E. | jor | 5.000000 | $1,224.89 | $6,124.45 |
| CUA-CUADRILLA NO-11 | Cuadrilla 1 of.soldador + 1 ayudante E. | jor | 5.000000 | $1,224.89 | $6,124.45 |
| CUA-CUADRILLA NO-12 | Cuadrilla de 1 of.montador + 4 ayudante A. | jor | 5.000000 | $2,431.02 | $12,155.10 |
| Suma de Mano de Obra | $24,404.00 | ||||
| Equipo | |||||
| CHE-EQUIPO-027 | Equipo de corte de oxi-butano | HR | 8.000000 | $8.47 | $67.76 |
| CHE-EQUIPO-034 | Esmeriladora | HR | 4.000000 | $2.88 | $11.52 |
| CHE-EQUIPO-002 | SOLDADORA LINCOLN SAE 300 AMP. K 1277 MOT. PERKINS 4236, 4 CIL. 60 HP. 1600 R.P.M. | HR | 10.000000 | $8.70 | $87.00 |
| Suma de Equipo | $166.28 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORROSIVO | M2 | 10.000000 | $49.09 | $490.90 |
| PINTUR-ESMALTE | APLICACION DE PINTURA DE ESMALTE COMEX 100.00 | M2 | 10.000000 | $123.33 | $1,233.30 |
| Suma de Auxiliar | $1,724.20 | ||||
| Costo Directo | $50,312.48 |