| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O PROV | TRABAJOS ELECTRICOS PROVISIONALES QUE INCLUYE: SUBESTACION ELECTRICA PROVISIONAL DE 112.5 KVA, MONTAJE Y CONEXIONES EN SUBESTACION TIPO POSTE Y TABLEROS DE BAJA TENSION DENTRO DE LA TIENDA PARA PROPORCIONAR ENERGIA A CONTRATISTAS(NO SE INCLUYE DENTRO DEL PRESUPUESTO) | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| RENTA DE TRANSORMADO | 112.5 KVA | MES | 2.000000 | $18,900.00 | $37,800.00 |
| HERRAJES | HERRAJES | LOTE | 1.000000 | $18,687.00 | $18,687.00 |
| CABLE THW-LS CAL.10. | CABLE THWLS DE CAL. 10 AWG, 600 V CONDUMEX | ML | 250.000000 | $3.85 | $962.50 |
| CABLE THW CALIBRE 8. | CABLE THW-LS CALIBRE 8 MARCA CONDUMEX | ML | 200.000000 | $6.90 | $1,380.00 |
| CABLE THW-LS CAL. 6 | CABLE THW-LS CALIBRE 6 MARCA CONDUMEX | Ml | 200.000000 | $9.50 | $1,900.00 |
| CABLE THW-LS CAL. 4 | CABLE THW-LS CALIBRE 4 MARCA CONDUMEX | ML | 200.000000 | $14.36 | $2,872.00 |
| CABLE THWN CAL. 1/0 | CABLE THWN CAL. 1/0 CONDUMEX | ML | 300.000000 | $38.85 | $11,655.00 |
| CABLE 2/0 | CABLE 2/0 condumex | ML | 150.000000 | $49.00 | $7,350.00 |
| INT I LINE FA36070 | INTERRUPTOR I LINE FA36070 | PZA | 2.000000 | $2,206.00 | $4,412.00 |
| INT I LINE FA 360150 | PZA | 1.000000 | $4,750.00 | $4,750.00 | |
| Suma de Material | $91,768.50 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 61.520000 | $775.62 | $47,716.14 |
| Suma de Mano de Obra | $47,716.14 | ||||
| Costo Directo | $139,484.64 |