| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 330 | CERRAMIENTO DE 20 X 20 CMS. ARMADO CON 4 VR No 3 Y ESTRIBOS No 2 @25 CMS. CONCRETO F'C=150 KG/CM2. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO REF.VAR.DIAM. | ACERO DE REFUERZO | KG | 2.460000 | $8.20 | $20.17 |
| ACERO ALAM | ALAMBRON DE 1/4" | KG | 1.170000 | $10.00 | $11.70 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.069000 | $12.00 | $0.83 |
| CONC.PREMEZ.F-C=200 | CONCRETO PREMEZCLADO F'C= 200 KG/CM2 | M3 | 0.033000 | $991.90 | $32.73 |
| Suma de Material | $65.43 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | (1 Of. Albañil + 1 Peon) | jor | 0.110000 | $763.77 | $84.01 |
| Suma de Mano de Obra | $84.01 | ||||
| Auxiliar | |||||
| CIMBRA APARENTE | CIMBRA APARENTE | M2 | 0.400000 | $158.00 | $63.20 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $63.20 | ||||
| Costo Directo | $212.65 |