| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PISOS-01 | PISO DE 14 CM. DE ESPESOR CONCRETO PREMEZCLADO MR-38, ACABADO PULIDO VACIADO CON BOMBA, INCLUYE: TRAZO, NIVELACION, EXCAVACION, CIMBRA, DESCIMBRA, VIBRADO A REGLA VIBRADORA, CURADO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CHE-CONCRETO-021 | CONCRETO PREMEZCLADO MR - 38 | M3 | 0.140500 | $994.84 | $139.78 |
| CHE-CIMBRA-01 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.900000 | $11.40 | $10.26 |
| CHE-CONCRETO-05 | BOMBEO DE CONCRETO | m3 | 0.140500 | $139.84 | $19.65 |
| CHE-CONCRETO-03 | SOBRE PRECIO POR REV. 14-16 CM AGREG. 3/4" APTO PARA BOMB.(A) | M3 | 0.140500 | $59.28 | $8.33 |
| CHE-ACERO- 6X6/6-6 | MALLA ELECTROSOLDADA 6X6 | M2 | 1.050000 | $29.82 | $31.31 |
| Suma de Material | $209.32 | ||||
| Mano de Obra | |||||
| CUA-CHE-06 | CUADRILLA ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.045000 | $2,804.19 | $126.19 |
| Suma de Mano de Obra | $126.19 | ||||
| Equipo | |||||
| CHE-EQUIPO-028 | REGLA VIBRATORIA | HR | 0.032053 | $172.10 | $5.52 |
| Suma de Equipo | $5.52 | ||||
| Auxiliar | |||||
| CHE-CIMBRA-PISO | CIMBRA EN PISOS DE CONCRETO DE 15 CMS DE ESPESOR INCLUYE CHAFLAN Y PERFORACIONES A CADA 60 CMS PARA PASAJUNTAS | M2 | 1.000000 | $37.13 | $37.13 |
| Suma de Auxiliar | $37.13 | ||||
| Costo Directo | $378.16 |