| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2804-028 | SUMINISTRO Y APLICACION DE PINTURA DE MCA SHERWIN WILLIAMS, EN PLAFONES RETICULARES DE TABLA-ROCA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA ESMALTE SW-1 | PINTURA DE ESMALTE SHERWIN WILLIAMS COLOR TAMPETINT 2010 | LT | 0.250000 | $57.49 | $14.37 |
| THINER | THINER | LT | 0.150000 | $12.00 | $1.80 |
| Suma de Material | $16.17 | ||||
| Mano de Obra | |||||
| CUAD OC 18 | (1 Of. Pintor +2 Ayudante). | JOR | 0.025000 | $963.99 | $24.10 |
| Suma de Mano de Obra | $24.10 | ||||
| Auxiliar | |||||
| TORRE HIDRAULICA | MODULO DE 5.5 MTS PARA INSTALACIONES, CON LLANTAS | R/D | 0.040000 | $0.00 | $0.00 |
| Suma de Auxiliar | $0.00 | ||||
| Costo Directo | $40.27 |