| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 49-EX | SOPORTE METALICO PARA EXTRACTOR EN AZOTEA, A BASE DE PERFIL PTR, Y PLACA DE ACERO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL PTR | PERFIL ESTRUCTURAL PTR | KG | 163.030000 | $9.50 | $1,548.79 |
| PLACA DE ACERO | PLACA 1/4" ACERO | KG | 8.240000 | $11.00 | $90.64 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 1.500000 | $30.00 | $45.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 2.000000 | $4.05 | $8.10 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.800000 | $40.00 | $32.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.100000 | $31.25 | $3.13 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 2.000000 | $47.00 | $94.00 |
| THINER | THINER | LT | 1.500000 | $12.00 | $18.00 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 2.400000 | $67.00 | $160.80 |
| Suma de Material | $2,000.45 | ||||
| Mano de Obra | |||||
| CUAD OC 39 | (1 Of. Pailero + 1 Ayud.) | jor | 2.000000 | $783.30 | $1,566.60 |
| CUAD OC 18 | (1 Of. Pintor +2 Ayudante). | JOR | 0.700000 | $963.99 | $674.79 |
| Suma de Mano de Obra | $2,241.39 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 2.000000 | $31.60 | $63.20 |
| ESMERILADORA | Esmeriladora | HR | 1.000000 | $10.06 | $10.06 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 1.000000 | $0.59 | $0.59 |
| Suma de Equipo | $73.85 | ||||
| Costo Directo | $4,315.69 |