| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| I.2 | SUMINSTRO, HABILITADO, FABRICACION Y MONTAJE DE ESTRUCTURAS METALICA A BASE DE DE PLACA A-36; INCLUYE: MATERIALES, DESPERDICIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO. UNA MANO DE PRIMARIO ANTICORROSIVO DE TALLER. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PLACA A36 1/4"-1/2" | PLACA A36 1/4"-1/2" | KG | 0.491000 | $16.50 | $8.10 |
| PLACA A36 3/4"-1" | PLACA A36 3/4"-1" | KG | 0.594000 | $15.50 | $9.21 |
| GAS P/ CORTES | GAS P/ CORTES | KG | 0.009000 | $8.70 | $0.08 |
| OXIGENO | OXIGENO | M3 | 0.013000 | $19.00 | $0.25 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.030000 | $45.00 | $1.35 |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002200 | $45.00 | $0.10 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.007849 | $0.00 | $0.00 |
| Suma de Material | $19.08 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.003509 | $597.47 | $2.10 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.003510 | $597.47 | $2.10 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.002761 | $1,069.04 | $2.95 |
| Suma de Mano de Obra | $7.15 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | Equipo de corte de oxi-butano | HR | 0.013880 | $9.56 | $0.13 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $2.88 | $0.08 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.011440 | $12.48 | $0.14 |
| GRUA | Grua de 20 ton. | HR | 0.003681 | $371.86 | $1.37 |
| Suma de Equipo | $1.73 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORR | PRIMARIO ANTICORR | M2 | 0.035000 | $33.56 | $1.17 |
| Suma de Auxiliar | $1.17 | ||||
| Costo Directo | $29.13 |