| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.9.50 | SUMINISTRO E INSTALACIÓN DE BOMBA SUMERGIBLE PARA 40 LPS Y 80.8 MCA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| EQBMBAA | BOMBA SUMERGIBLE 40 LPS Y 80.8 MCA. | lote | 1.000000 | $70,534.55 | $70,534.55 |
| Suma de Material | $70,534.55 | ||||
| Mano de Obra | |||||
| CDRLL-EL3 | CUADRILLA ELECTRICISTAS 3 | jor | 0.775874 | $917.18 | $711.62 |
| 1I2EI | CUADRILLA No 18 (1.00 OF. INST. + 2.00 AY.ESP.) | jor | 0.444007 | $1,039.41 | $461.51 |
| Suma de Mano de Obra | $1,173.12 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.703029 | $163.91 | $115.23 |
| QAGR002 | GRUA | hora | 0.682790 | $253.49 | $173.08 |
| Suma de Equipo | $288.31 | ||||
| Costo Directo | $71,995.99 |