| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4.41.18 | SUMINISTRO E INSTALACIÓN DE TEE DE PVC METR 200 MM C-7 CEM. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0768757A | T HID METR 200-200 MM CEM TC 7 | PZ | 1.000000 | $713.99 | $713.99 |
| 9700254 | CEMENTO AGRICOLA 480 ML | PZ | 1.050000 | $24.80 | $26.04 |
| 9700130 | LIMPIADOR REXOLIT .500 LTS. | PZ | 0.630000 | $8.82 | $5.56 |
| Suma de Material | $745.59 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.076800 | $749.35 | $57.55 |
| Suma de Mano de Obra | $57.55 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.036140 | $163.91 | $5.92 |
| Suma de Equipo | $5.92 | ||||
| Costo Directo | $809.06 |