| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4.44.44 | SUMINISTRO E INSTALACIÓN DE CURVA DE PVC METR 90° X 200 MM C-7 CEM. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0768173C | CURVA HID METR. 90 200 MM TC 7 CEM | PZ | 1.000000 | $605.30 | $605.30 |
| 9700254 | CEMENTO AGRICOLA 480 ML | PZ | 0.700000 | $24.80 | $17.36 |
| 9700130 | LIMPIADOR REXOLIT .500 LTS. | PZ | 0.420000 | $8.82 | $3.70 |
| Suma de Material | $626.36 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA No.24 (1.00 OF. INST.+ 1.00 AY.ESP.) | jor | 0.053380 | $749.35 | $40.00 |
| Suma de Mano de Obra | $40.00 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.024500 | $163.91 | $4.02 |
| Suma de Equipo | $4.02 | ||||
| Costo Directo | $670.38 |