| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.9.75 | SUMINISTRO E INSTALACIÓN DE BOMBA SUMERGIBLE 52 LPS Y 78 MCA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| EQBMBAA | BOMBA SUMERGIBLE 52 LPS Y 78 MCA. | lote | 1.000000 | $89,174.36 | $89,174.36 |
| Suma de Material | $89,174.36 | ||||
| Mano de Obra | |||||
| CDRLL-EL3 | CUADRILLA ELECTRICISTAS 3 | jor | 0.992170 | $917.18 | $910.00 |
| 1I2EI | CUADRILLA No 18 (1.00 OF. INST. + 2.00 AY.ESP.) | jor | 0.517360 | $1,039.41 | $537.75 |
| Suma de Mano de Obra | $1,447.75 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS2 | CAMIONETA PICK UP MCA NISSAN | hora | 0.838990 | $163.90 | $137.51 |
| QAGR002 | GRUA GROVE IND-36 | hora | 0.897486 | $253.46 | $227.48 |
| Suma de Equipo | $364.99 | ||||
| Costo Directo | $90,987.09 |