| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 560.2.026 | BARANDAL CON TUBO DE 1" Y 2" CEDULA 40 EN RAMPA DE SALIDA DE EMERGENCIA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO GALV 2" | TUBO GALV. 2" CEDULA 40 | ML | 0.380000 | $105.00 | $39.90 |
| TUBO GALV 1" | TUBO GALV. 1" CEDULA 40 | ML | 0.710000 | $70.00 | $49.70 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.200000 | $30.00 | $6.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.100000 | $4.05 | $0.41 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.200000 | $40.00 | $8.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.100000 | $31.25 | $3.13 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 0.100000 | $47.00 | $4.70 |
| THINER | THINER | LT | 0.100000 | $12.00 | $1.20 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 0.160000 | $67.00 | $10.72 |
| Suma de Material | $123.75 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | CUAD. 1 OF. PAILERO + 1 AYUDANTE. | jor | 0.150000 | $791.06 | $118.66 |
| CUAD OC PINT | CUAD. 1 OF. PINTORr + 2 AYUDANTES. | jor | 0.040000 | $1,094.69 | $43.79 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.015000 | $771.14 | $11.57 |
| Suma de Mano de Obra | $174.01 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.100000 | $31.60 | $3.16 |
| ESMERILADORA | Esmeriladora | HR | 0.100000 | $10.08 | $1.01 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.100000 | $0.59 | $0.06 |
| Suma de Equipo | $4.23 | ||||
| Costo Directo | $301.99 |