| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 270.5.E22 | ESCALERA DE SERVICIO A CUBIERTA, CON COMPUERTA FINAL DE LA MISMA, FORMADA CON, INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA, EQUIPO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL PTR | PERFIL ESTRUCTURAL PTR | KG | 180.000000 | $9.50 | $1,710.00 |
| ANGULO DIF. MEDIDAS | ANGULO METALICO | KG | 19.000000 | $10.00 | $190.00 |
| LAMINA CAL 20 | LAMINA LISA CAL. 20 | kg | 7.000000 | $20.00 | $140.00 |
| LAMINA ANTIDERRAPANT | LAMINA ANTIDERRPANTE GR-1500 | M2 | 2.400000 | $631.00 | $1,514.40 |
| LAM.PINTRO C-22 | LAMINA PINTRO CAL. 22 | M2 | 1.950000 | $120.00 | $234.00 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 4.500000 | $30.00 | $135.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 2.000000 | $4.05 | $8.10 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.800000 | $40.00 | $32.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.200000 | $31.25 | $6.25 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 3.500000 | $47.00 | $164.50 |
| THINER | THINER | LT | 2.500000 | $12.00 | $30.00 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 4.000000 | $67.00 | $268.00 |
| Suma de Material | $4,432.25 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | CUAD. 1 OF. PAILERO + 1 AYUDANTE. | jor | 5.000000 | $791.06 | $3,955.30 |
| CUAD OC PINT | CUAD. 1 OF. PINTORr + 2 AYUDANTES. | jor | 1.600000 | $1,094.69 | $1,751.50 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 2.000000 | $771.14 | $1,542.28 |
| Suma de Mano de Obra | $7,249.08 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 3.000000 | $31.60 | $94.80 |
| ESMERILADORA | Esmeriladora | HR | 2.000000 | $10.08 | $20.16 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 2.000000 | $0.59 | $1.18 |
| Suma de Equipo | $116.14 | ||||
| Costo Directo | $11,797.47 |