| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 280.8.007 | SUMINISTRO Y COLOCACION DE ANGULO DE 1"X1"X1/8" EN RANURA DE PISO EN VESTIBULO, PARA RECIBIR CONTRA BARRETA Y SOLERA DE REMATE DE CORTINA. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANGULO DIF. MEDIDAS | ANGULO METALICO | KG | 1.100000 | $10.00 | $11.00 |
| PLACA DE ACERO | PLACA 1/4" ACERO | KG | 0.100000 | $11.00 | $1.10 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.020000 | $30.00 | $0.60 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.010000 | $4.05 | $0.04 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.020000 | $40.00 | $0.80 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.010000 | $31.25 | $0.31 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 0.010000 | $47.00 | $0.47 |
| THINER | THINER | LT | 0.010000 | $12.00 | $0.12 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 0.016000 | $67.00 | $1.07 |
| Suma de Material | $15.52 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | CUAD. 1 OF. PAILERO + 1 AYUDANTE. | jor | 0.015000 | $791.06 | $11.87 |
| CUAD OC PINT | CUAD. 1 OF. PINTORr + 2 AYUDANTES. | jor | 0.003000 | $1,094.69 | $3.28 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.001500 | $771.14 | $1.16 |
| Suma de Mano de Obra | $16.31 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.010000 | $31.60 | $0.32 |
| ESMERILADORA | Esmeriladora | HR | 0.010000 | $10.08 | $0.10 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.010000 | $0.59 | $0.01 |
| Suma de Equipo | $0.42 | ||||
| Costo Directo | $32.24 |