| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 270.1-007 | CONEXION DE MURO INTERIOR A LOSA DE CIMENTACION , CON DENTELLON Y CADENA DE DESPLANTE. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO MR-40 | CONCRETO PROFESIONAL MR = 40 KG/CM2 MODULO DE RUPTURA, ESPECIAL PARA PAVIMENTOS CON RESISTENCIA A LA FLEXION, DE 15 CMS. DE ESPESOR | m3 | 0.192500 | $1,300.00 | $250.25 |
| ACERO ALAM | ALAMBRON DE 1/4" | KG | 1.050000 | $10.00 | $10.50 |
| ACERO REF.VAR.DIAM. | ACERO DE REFUERZO | KG | 14.710000 | $8.20 | $120.62 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 1.100000 | $11.00 | $12.10 |
| MADERA DE PINO DE 3A | MADERA DE PINO DE 3a. | PT | 0.200000 | $7.50 | $1.50 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 0.050000 | $95.00 | $4.75 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.010000 | $13.00 | $0.13 |
| Suma de Material | $399.85 | ||||
| Mano de Obra | |||||
| CUAD OC 01 | (1 peón) | jor | 0.083333 | $341.26 | $28.44 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.050000 | $771.14 | $38.56 |
| CUAD OC 11 | CUAD. 1 OF. CARPINTERO O.N. + 1AYTE. | jor | 0.025000 | $771.14 | $19.28 |
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | jor | 0.100000 | $771.14 | $77.11 |
| Suma de Mano de Obra | $163.39 | ||||
| Costo Directo | $563.24 |