| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| W22003-01 | TERRAPLEN CON MATERIAL INERTE, DE HASTA 2.00 M. DE ALTURA, PARA FORMACION DE PLATAFORMA. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| RELLENO LIMPIO | RELLENO LIMPIO | M3 | 1.300000 | $90.00 | $117.00 |
| Suma de Material | $117.00 | ||||
| Equipo | |||||
| CAMION PIPA DODGE P | CAMION PIPA DODGE PARA 8000 LITROS MOTOR DIESEL 140 H.P. | HR | 0.013000 | $441.40 | $5.74 |
| MOTOCONFORMADORA | MOTOCONFORMADORA | HR | 0.045000 | $699.37 | $31.47 |
| PATA DE CABRA | COMPACTADOR PATA DE CABRA | HR | 0.020000 | $428.68 | $8.57 |
| MAQUINARIA-01 | TRACTOR SOBRE ORUGAS MOD. D-53A-16 | HR | 0.020000 | $781.85 | $15.64 |
| Suma de Equipo | $61.42 | ||||
| Costo Directo | $178.42 |