| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 270.3-010 | DALA DE CERRAMIENTO DE 15 X 30 CM. CONCRETO F C=200 KG/CM2 , EN MURO PERIMETRAL, ARMADA CON 4 VAR. DEL No. 3 Y ESTR. DEL No. 2 @ 15 CM, INCLUYE: CIMBRA, DESCIMRA, ACARREOS, EQUIPO, HERRAMIENTA Y MANO DE OBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO REF.VAR.DIAM. | ACERO DE REFUERZO | KG | 2.460000 | $8.20 | $20.17 |
| ACERO ALAM | ALAMBRON DE 1/4" | KG | 1.170000 | $10.00 | $11.70 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.069000 | $11.00 | $0.76 |
| CONC.PREMEZ.F-C=200 | CONCRETO PREMEZCLADO F'C= 200 KG/CM2 | M3 | 0.049500 | $991.90 | $49.10 |
| Suma de Material | $81.73 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.142857 | $771.14 | $110.16 |
| Suma de Mano de Obra | $110.16 | ||||
| Auxiliar | |||||
| CIMBRA APARENTE | CIMBRA APARENTE | M2 | 0.600000 | $158.66 | $95.20 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $95.20 | ||||
| Costo Directo | $287.09 |