| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 270.5.004 | ESCALERA INTERIOR DE ACCESO HACIA GERENCIA, CON 6 ESCALONES DE 0.30 M. DE HUELLA, 0.18 M. DE PERALTE POR 1.60 M. DE ANCHO, DESCANSO DE 1.50 X 1.60 M., ESCALONES DE LAMINA GALV. CAL. 14, MODELO BOLITA, ANGULO DE SOPORTE DE ESCALON DE 3" X 4", ALFARDA METALICA, 1 CPS DE 10" X 31/2", PTR LIGERO DE 4", ANCLADA LA ESCALERA A PISO POR MEDIO DE PLACA, 0.45 X 0.17 X 1/2" DE ESPESOR, BARANDAL FORMADO POR TUBOS CED. 30 DE 2" Y 1" Y LAMINA PERFO-RED CAL. 22 GALVANIZADA MOD. DIAMANTE, EN CARAS. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LAMINA ANTIDERRAPANT | LAMINA ANTIDERRPANTE GR-1500 | M2 | 5.880000 | $631.00 | $3,710.28 |
| ANGULO DIF. MEDIDAS | ANGULO METALICO | KG | 68.000000 | $10.00 | $680.00 |
| PERFIL PTR | PERFIL ESTRUCTURAL PTR | KG | 67.600000 | $9.50 | $642.20 |
| PERFIL APS | PERFIL ESTRUCTURAL APS | KG | 191.180000 | $10.00 | $1,911.80 |
| PLACA DE ACERO | PLACA 1/4" ACERO | KG | 25.240000 | $11.00 | $277.64 |
| REDONDO LISO | REDONDO LISO | KG | 2.350000 | $11.00 | $25.85 |
| TUBO GALV 1" | TUBO GALV. 1" CEDULA 40 | ML | 14.500000 | $70.00 | $1,015.00 |
| TUBO GALV 2" | TUBO GALV. 2" CEDULA 40 | ML | 34.000000 | $105.00 | $3,570.00 |
| LAMINA PERFO-RED C22 | LAMINA PERFO-RED. CALIBRE 22. | M2 | 4.080000 | $879.00 | $3,586.32 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 4.500000 | $30.00 | $135.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 5.600000 | $4.05 | $22.68 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 3.400000 | $40.00 | $136.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.600000 | $31.25 | $18.75 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 5.600000 | $47.00 | $263.20 |
| THINER | THINER | LT | 6.000000 | $12.00 | $72.00 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 7.000000 | $67.00 | $469.00 |
| Suma de Material | $16,535.72 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | CUAD. 1 OF. PAILERO + 1 AYUDANTE. | jor | 8.000000 | $791.06 | $6,328.48 |
| CUAD OC PINT | CUAD. 1 OF. PINTORr + 2 AYUDANTES. | jor | 4.000000 | $1,094.69 | $4,378.76 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 3.000000 | $771.14 | $2,313.42 |
| Suma de Mano de Obra | $13,020.66 | ||||
| Equipo | |||||
| SOLDADORA EST. | Soldadora Miller Dimension Mod. 652 | HR | 8.000000 | $31.60 | $252.80 |
| ESMERILADORA | Esmeriladora | HR | 10.000000 | $10.08 | $100.80 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 8.000000 | $0.59 | $4.72 |
| Suma de Equipo | $358.32 | ||||
| Costo Directo | $29,914.70 |