| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| II.01B).- | DE 2 VIAS DE 101 MM. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C PVC PES 101MM | TUBO CONDUIT DE P.V.C. PESADO DE 101 mm (4") DE DIAM MCA REX. | ML | 2.100000 | $48.95 | $102.80 |
| CONCRETO F-C=100 H/O | Concreto hecho en obra f'c = 100 kg/cm2agregado max. 3/4" R.N. | M3 | 0.105000 | $754.52 | $79.22 |
| CAL | CALHYDRA | TON | 0.001250 | $853.00 | $1.07 |
| CARRETE-PLAST | CARRETE DE HILO DE PLASTICO PARA TRAZO CALIBRE 10 | ROLL | 0.002500 | $18.00 | $0.05 |
| PEGAMENTO TANGIT PVC | PEGAMENTO TANGIT PVC BOTE 250 ml | PZA | 0.058000 | $99.81 | $5.79 |
| LIMPIADOR PVC | Limpiador de PVC bote de 250 ml | PZA | 0.058000 | $32.00 | $1.86 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.160000 | $9.50 | $1.52 |
| ESTOPA | ESTOPA | Kg. | 0.160000 | $17.50 | $2.80 |
| SEGUETA STANDAR | SEGUETA STANDAR | PZA | 0.200000 | $8.00 | $1.60 |
| Suma de Material | $196.70 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 topografo + 2 cadeneros) | JOR | 0.003324 | $1,223.83 | $4.07 |
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.076923 | $877.76 | $67.52 |
| CUADRILLA NO. 02 | (1 Of. Albanil + 1 Peón) | JOR | 0.100000 | $629.93 | $62.99 |
| Suma de Mano de Obra | $134.58 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETROEXCAVADORA | RETROEXCAVADORA | HR | 0.018750 | $138.19 | $2.59 |
| CAMION DE VOLTEO. | CAMION DE VOLTEO DE 7 M3 | HR | 0.006225 | $251.03 | $1.56 |
| CORTADORA | CORTADORA DE PISO CON DISCO | HR | 0.020000 | $115.68 | $2.31 |
| TRANSITO | TRANSITO PARA MEDICION K-E, MODELO CH5 | HR | 0.041000 | $10.08 | $0.41 |
| Suma de Equipo | $6.88 | ||||
| Auxiliar | |||||
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 0.810000 | $16.96 | $13.74 |
| Suma de Auxiliar | $13.74 | ||||
| Costo Directo | $351.89 |