| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| II.01A).- | DE 1 VIAS DE 50 MM | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C PVC PES 51 MM | TUBO CONDUIT DE P.V.C. PESADO DE 51 mm (2") DE DIAM MCA REX. | ML | 1.050000 | $20.20 | $21.21 |
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.052500 | $863.60 | $45.34 |
| CAL | CALHYDRA | TON | 0.001250 | $853.00 | $1.07 |
| CARRETE-PLAST | CARRETE DE HILO DE PLASTICO PARA TRAZO CALIBRE 10 | ROLL | 0.002500 | $18.00 | $0.05 |
| PEGAMENTO TANGIT PVC | PEGAMENTO TANGIT PVC BOTE 250 ml | PZA | 0.014500 | $99.81 | $1.45 |
| LIMPIADOR PVC | Limpiador de PVC bote de 250 ml | PZA | 0.014500 | $32.00 | $0.46 |
| ESTOPA | ESTOPA | Kg. | 0.040000 | $17.50 | $0.70 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.040000 | $9.50 | $0.38 |
| SEGUETA STANDAR | SEGUETA STANDAR | PZA | 0.050000 | $8.00 | $0.40 |
| Suma de Material | $71.05 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 topografo + 2 cadeneros) | JOR | 0.003324 | $1,223.83 | $4.07 |
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.039790 | $877.76 | $34.93 |
| CUADRILLA NO. 02 | (1 Of. Albanil + 1 Peón) | JOR | 0.100000 | $629.93 | $62.99 |
| Suma de Mano de Obra | $101.99 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| RETROEXCAVADORA | RETROEXCAVADORA | HR | 0.018750 | $138.19 | $2.59 |
| CAMION DE VOLTEO. | CAMION DE VOLTEO DE 7 M3 | HR | 0.006225 | $251.03 | $1.56 |
| CORTADORA | CORTADORA DE PISO CON DISCO | HR | 0.020000 | $115.68 | $2.31 |
| TRANSITO | TRANSITO PARA MEDICION K-E, MODELO CH5 | HR | 0.041000 | $10.08 | $0.41 |
| Suma de Equipo | $6.88 | ||||
| Auxiliar | |||||
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 0.752000 | $16.96 | $12.75 |
| Suma de Auxiliar | $12.75 | ||||
| Costo Directo | $192.67 |