| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| I.05B).- | DE 19 MM. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C PVC PES 19 MM | TUBO CONDUIT DE P.V.C. PESADODE DIAMETRO 19 mm (3/4") MCA. REX | ML | 1.050000 | $8.10 | $8.51 |
| ABRAZ UÑA 19 MM | ABRAZADERA UÑA 19 MM | PZA | 0.666667 | $4.39 | $2.93 |
| CODO C PVC PES 19 MM | CODO CONDUIT DE P.V.C. PESADODE DIAMETRO 19 mm (3/4") MCA. REX | PZA | 0.130058 | $13.20 | $1.72 |
| CAJA REG PVC PES 4X4 | CAJA CUADRADA P.V.C. REFORZADA DE 4X4, CON TAPA CIEGA MCA. REX | PZA | 0.043353 | $28.90 | $1.25 |
| PEGAMENTO TANGIT PVC | PEGAMENTO TANGIT PVC BOTE 250 ml | PZA | 0.013000 | $99.81 | $1.30 |
| LIMPIADOR PVC | Limpiador de PVC bote de 250 ml | PZA | 0.013000 | $32.00 | $0.42 |
| ESTOPA | ESTOPA | Kg. | 0.025000 | $17.50 | $0.44 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.025000 | $9.50 | $0.24 |
| SEGUETA STANDAR | SEGUETA STANDAR | PZA | 0.035000 | $8.00 | $0.28 |
| Suma de Material | $17.07 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.026316 | $877.76 | $23.10 |
| Suma de Mano de Obra | $23.10 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.020000 | $49.36 | $0.99 |
| Suma de Auxiliar | $0.99 | ||||
| Costo Directo | $41.16 |