| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.2.5.5 | T CEM 75-75-13 MM | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0306098 | T HID CEM. 75 MM | PZ | 1.000000 | $64.43 | $64.43 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.225000 | $17.46 | $3.93 |
| 9700254 | CEMENTO 480 ML | PZ | 0.376000 | $52.91 | $19.89 |
| 0309210 | REDUC. HID CEM. BUSH. 75- 50 MM. | PZ | 1.000000 | $16.43 | $16.43 |
| 0309155 | REDUC. HID CEM. BUSH. 50- 25 MM. | PZ | 1.000000 | $5.38 | $5.38 |
| Suma de Material | $110.06 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.035211 | $782.19 | $27.54 |
| Suma de Mano de Obra | $27.54 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.006018 | $191.15 | $1.15 |
| Suma de Equipo | $1.15 | ||||
| Costo Directo | $138.75 |