| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9017555 | TUBO IRRIGACION ABOC CEM 32 MM C/L | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0301127 | TUBO HID S/I RD-26 32 MM 6M C/B | MT | 1.000000 | $6.80 | $6.80 |
| 0301127 | TUBO HID S/I RD-26 32 MM 6M C/B | MT | 1.000000 | $6.80 | $6.80 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.010000 | $17.46 | $0.17 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.010000 | $17.46 | $0.17 |
| 9700254 | CEMENTO 480 ML | PZ | 0.020000 | $52.91 | $1.06 |
| 9700254 | CEMENTO 480 ML | PZ | 0.020000 | $52.91 | $1.06 |
| Suma de Material | $16.07 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.003785 | $782.19 | $2.96 |
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.003785 | $782.19 | $2.96 |
| Suma de Mano de Obra | $5.92 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.000646 | $191.15 | $0.12 |
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.000646 | $191.15 | $0.12 |
| Suma de Equipo | $0.25 | ||||
| Costo Directo | $22.23 |