| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9003164 | REDUCC H.C.BUSH. 75-50 mm. | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0309210 | REDUC. HID CEM. BUSH. 75- 50 MM. | PZ | 1.000000 | $16.43 | $16.43 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.160000 | $17.46 | $2.79 |
| 9700254 | CEMENTO 480 ML | PZ | 0.255000 | $52.91 | $13.49 |
| Suma de Material | $32.72 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.012807 | $782.19 | $10.02 |
| Suma de Mano de Obra | $10.02 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.002195 | $191.15 | $0.42 |
| Suma de Equipo | $0.42 | ||||
| Costo Directo | $43.15 |