| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9011965 | COPLE HIDR CEM 32 MM C/L | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0303058 | COPLE HID CEM. 32 MM | PZ | 1.000000 | $4.27 | $4.27 |
| 0303058 | COPLE HID CEM. 32 MM | PZ | 1.000000 | $4.27 | $4.27 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.024000 | $17.46 | $0.42 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.024000 | $17.46 | $0.42 |
| 9700254 | CEMENTO 480 ML | PZ | 0.040000 | $52.91 | $2.12 |
| 9700254 | CEMENTO 480 ML | PZ | 0.040000 | $52.91 | $2.12 |
| Suma de Material | $13.61 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.003785 | $782.19 | $2.96 |
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.003785 | $782.19 | $2.96 |
| Suma de Mano de Obra | $5.92 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.000646 | $191.15 | $0.12 |
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.000646 | $191.15 | $0.12 |
| Suma de Equipo | $0.25 | ||||
| Costo Directo | $19.78 |