| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9008970 | T CEM. 100-100- 75 MM. | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0306103 | T HID CEM. 100 MM | PZ | 1.000000 | $102.52 | $102.52 |
| 0306103 | T HID CEM. 100 MM | PZ | 1.000000 | $102.52 | $102.52 |
| 0309272 | REDUC. HID CEM. BUSH. 100- 75 MM. | PZ | 1.000000 | $28.28 | $28.28 |
| 0309272 | REDUC. HID CEM. BUSH. 100- 75 MM. | PZ | 1.000000 | $28.28 | $28.28 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.297000 | $17.46 | $5.19 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.297000 | $17.46 | $5.19 |
| 9700254 | CEMENTO 480 ML | PZ | 0.495000 | $52.91 | $26.19 |
| 9700254 | CEMENTO 480 ML | PZ | 0.495000 | $52.91 | $26.19 |
| Suma de Material | $324.35 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.042917 | $782.19 | $33.57 |
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.042917 | $782.19 | $33.57 |
| Suma de Mano de Obra | $67.14 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.007309 | $191.15 | $1.40 |
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.007309 | $191.15 | $1.40 |
| Suma de Equipo | $2.79 | ||||
| Costo Directo | $394.28 |