| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E.83 | DALA | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: , REVENIMIENTO 12-14. | m3 | 1.050000 | $825.00 | $866.25 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 1.050000 | $135.00 | $141.75 |
| AGUA | AGUA | m3 | 0.250000 | $50.00 | $12.50 |
| Suma de Material | $1,020.50 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-03 | (1 OFICIAL ALBAÑIL + 5 AYUDANTES). | jor | 0.160000 | $1,532.26 | $245.16 |
| Suma de Mano de Obra | $245.16 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hr | 0.250000 | $16.96 | $4.24 |
| Suma de Equipo | $4.24 | ||||
| Concepto | |||||
| CIM-APAR | CIMBRA DE CONTACTO EN ELEMENTOS APARENTES (ESTRUCTURA) | m2 | 3.333300 | $137.65 | $458.83 |
| Suma de Concepto | $458.83 | ||||
| Costo Directo | $1,728.73 |