| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1409 | Señales informativas de destino b) SID-9 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0093-00 | Soldadura E-7018 | kg | 1.300000 | $46.33 | $60.23 |
| 02-0817-00 | Primario Anticorrosivo | lt | 0.400000 | $67.00 | $26.80 |
| 02-0815-00 | Estopa | kg | 0.250000 | $28.97 | $7.24 |
| 02-0820-00 | Papel Kraft | kg | 0.060000 | $9.00 | $0.54 |
| 02-0821-00 | Bajo alfombra poli-pad | m2 | 0.100000 | $6.50 | $0.65 |
| 02-0823-01 | Monten en canal 6" x 6" cal. 6 >>4.2m*25.5 kg/m*1.03 desp=110.3130 kg | kg | 110.313000 | $10.53 | $1,161.60 |
| 02-0810-00 | Scotch lite grado ingenieria blanco | m2 | 0.640000 | $207.45 | $132.77 |
| 02-0816-00 | Adelgazador thinner | lt | 1.600000 | $16.00 | $25.60 |
| 02-0085-01 | Pernos de anclaje de 1 1/2" diam. x 160 cm | pza | 6.000000 | $96.55 | $579.30 |
| Suma de Material | $1,994.73 | ||||
| Mano de Obra | |||||
| 01-1007-17 | Cuadrilla No. 7: oficial especialista + ayudante >>Rend=3 pza/jor | jor | 0.333333 | $674.55 | $224.85 |
| 01-1002-159 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion >>Rend=1.5 pza/jor | jor | 0.666700 | $265.42 | $176.96 |
| 01-1035-05 | Operario especialista (soldador de primera) >>Rend=3 pza/jor | jor | 0.333300 | $445.73 | $148.56 |
| Suma de Mano de Obra | $550.37 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 03-0140-006 | Compresor de 375 pcm, 122 hpmod. xa 175 atlas copco (chicago pneumatic de 315 pcm 140 HP) >>PH=1.5 pza/hr | hora | 0.666700 | $169.44 | $112.97 |
| 03-0230-04 | Dobladora y cortadora de lamina y placa hasta 25mm de espesor Espamex PT 50-50 >>PH=2 pza/hr | hora | 0.500000 | $157.72 | $78.86 |
| 03-0231-04 | Taladro electrico manual bosh mod. 1182 >>PH=3.5 pza/hr | hora | 0.285700 | $1.72 | $0.49 |
| 03-0180-07 | Soldadora Lincoln SAE 300 amp. K1277 mot. Perkins 4236, 4 cil., 60 HP, 1600 rpm, (sin operador). >>PH-2.5 pza/hr | hora | 0.400000 | $63.52 | $25.41 |
| 03-0214-07 | Camioneta Pick-Up Ford F-250 8 cilindros 1.5 ton. 85 HP >>PH=4 pza/hr | hora | 0.250000 | $192.02 | $48.01 |
| Suma de Equipo | $265.73 | ||||
| Auxiliar | |||||
| 04-0711-05 | Perfil estructural rectangular P.T.R., incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. >>6.72m*4.54kg/m*1.03desp=31.4241 kg | kg | 31.424100 | $11.32 | $355.72 |
| 04-0106-02 | Concreto f'c=200 kg/cm2 hecho in-situ agreg. max. 38mm producidos por el contratista. >>0.4m*0.4m*1.03desp*2=0.3296m3 | m3 | 0.329600 | $1,167.55 | $384.82 |
| 04-0153-00 | Placa de acero A-36; incluye valor de adquisición carga + descarga + acarreo al 1er. km. y 49 kms. subsecuentes. | kg | 28.900000 | $13.82 | $399.40 |
| 04-0157-11 | Lamina galvanizada cal. 16; incluye va- tor de adquisicion carga + descarga + acarreo al 1er km y 49kms. subsecuentes. >>0.888m2*12.206 kg/m2*1.03deps=11.16 kg | ton | 0.011200 | $16,873.03 | $188.98 |
| Suma de Auxiliar | $1,328.92 | ||||
| Costo Directo | $4,139.74 |