| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1382 | Topes vibratorios de concreto | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0805-05 | 2) Metalicos, 250 usos. >>Moldes >>(3.1416*0.15m*1m)115m=0.0314m2/m | m2 | 0.031400 | $315.11 | $9.89 |
| Suma de Material | $9.89 | ||||
| Mano de Obra | |||||
| 01-1005-46 | Cuadrilla No. 5: albanil + peon >>Formacion del tope >>Rend=30 m/jor | jor | 0.033300 | $586.16 | $19.52 |
| Suma de Mano de Obra | $19.52 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| 04-0713-00 | Cajeo operacion. >>(5m*2.5m*lm)/15m=0.83m3/m Concreto f'c=150 kg/cm2 hecho in-situ | m3 | 0.833300 | $199.00 | $165.83 |
| 04-0105-01 | Concreto f'c=150 kg/cm2 hecho in-situ agreg. max. 38mm producidos por el tratista. >>4 cilindros de 15cm de diam. >>(0.7854*0.0225m2*5m)/15m=0.0059m3/m | m3 | 0.005900 | $1,099.24 | $6.49 |
| 04-0714-00 | Lechada de comento gris, inc. suministro en la obra de cemento y agua, con aca-- rreo de materiales al 1er. km y 49 kms. subsecuentes. | m3 | 0.003000 | $2,849.53 | $8.55 |
| 04-0709-00 | Vaciado y extendido de concreto. | m3 | 0.005900 | $195.66 | $1.15 |
| 04-0710-00 | Curado con agua | m3 | 0.005900 | $118.19 | $0.70 |
| Suma de Auxiliar | $182.71 | ||||
| Costo Directo | $212.13 |