| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1413 | Señales informativas de destino f) SID-13 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0823-03 | Monten en canal 10" x 10" cal. 6 >>3.9m*4.25kg/m*1.03desp=17.0723kg | kg | 17.072300 | $10.53 | $179.77 |
| 02-0824-01 | Placa de acero de 3/4" >>0.5m*0.5m*149.38kg/m2*1.03desp=38.46 kg | kg | 38.465400 | $13.50 | $519.28 |
| 02-0825-00 | Birlo de 1" diam. 12" prof. galv. | pza | 6.000000 | $76.91 | $461.46 |
| 02-0815-00 | Estopa | kg | 1.550000 | $28.97 | $44.90 |
| 02-0816-00 | Adelgazador thinner | lt | 9.800000 | $16.00 | $156.80 |
| 02-0817-00 | Primario Anticorrosivo | lt | 0.960000 | $67.00 | $64.32 |
| 02-0093-00 | Soldadura E-7018 | kg | 4.000000 | $46.33 | $185.32 |
| 02-0810-00 | Scotch lite grado ingenieria blanco | m2 | 0.970000 | $207.45 | $201.23 |
| 02-0821-00 | Bajo alfombra poli-pad | m2 | 0.300000 | $6.50 | $1.95 |
| 02-0820-00 | Papel Kraft | kg | 0.160000 | $9.00 | $1.44 |
| Suma de Material | $1,816.47 | ||||
| Mano de Obra | |||||
| 01-1007-20 | Cuadrilla No. 7: oficial especialista + ayudante >>Procesista >>Rend=0.9 pza/jor | jor | 1.100000 | $674.55 | $742.01 |
| 01-1002-163 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion >>Rend=3.5 pza/jor | jor | 0.280000 | $265.42 | $74.32 |
| 01-1035-08 | Operario especialista (soldador de primera) >>Rend=0.9 pza/jor | jor | 1.100000 | $445.73 | $490.30 |
| Suma de Mano de Obra | $1,306.63 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 03-0140-009 | Compresor de 375 pcm, 122 hpmod. xa 175 atlas copco (chicago pneumatic de 315 pcm 140 HP) >>PH=1.67 pza/hr | hora | 0.600000 | $169.44 | $101.66 |
| 03-0230-07 | Dobladora y cortadora de lamina y placa hasta 25mm de espesor Espamex PT 50-50 >>PH=1.25 pza/h | hora | 0.800000 | $157.72 | $126.18 |
| 03-0231-08 | Taladro electrico manual bosh mod. 1182 >>PH=3 pza/h | hora | 0.333300 | $1.72 | $0.57 |
| 03-0180-10 | Soldadora Lincoln SAE 300 amp. K1277 mot. Perkins 4236, 4 cil., 60 HP, 1600 rpm, (sin operador). >>PH=1 pza/hr | hora | 1.000000 | $63.52 | $63.52 |
| 03-0214-10 | Camioneta Pick-Up Ford F-250 8 cilindros 1.5 ton. 85 HP >>PH=2 pza/h | hora | 0.500000 | $192.02 | $96.01 |
| Suma de Equipo | $387.94 | ||||
| Auxiliar | |||||
| 04-0711-09 | Perfil estructural rectangular P.T.R., incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. >>9.0m*4.54kg/m*1.03desp=42.0858 kg | kg | 42.085800 | $11.32 | $476.41 |
| 04-0153-03 | Placa de acero A-36; incluye valor de adquisicion carga + descarga + acarreo al 1er. km. y 49 kms. subsecuentes. >>Cartabones. 2pza*0.045m2/pza*99.59kg/m2 >>*1.03desp=9.2320kg | kg | 9.232000 | $13.82 | $127.59 |
| 04-0157-15 | Lamina galvanizada cal. 16; incluye va- tor de adquisicion carga + descarga + acarreo al 1er km y 49kms. subsecuentes. >>3.709m2*12.206kg/m2*1.03desp=46.6302kg | ton | 0.046600 | $16,873.03 | $786.28 |
| 04-0106-04 | Concreto f'c=200 kg/cm2 hecho in-situ agreg. max. 38mm producidos por el contratista. >>0.6m*0.6m*1.03deps=0.3708m3 | m3 | 0.370800 | $1,167.55 | $432.93 |
| Suma de Auxiliar | $1,823.21 | ||||
| Costo Directo | $5,334.25 |