| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1412 | Señales informativas de destino e) SID-12 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0824-00 | Placa de acero de 3/4" >>0.5m*0.5m*149.38kg/m2*1.03desp*2=76.93kg | kg | 76.930700 | $13.50 | $1,038.56 |
| 02-0825-00 | Birlo de 1" diam. 12" prof. galv. | pza | 12.000000 | $76.91 | $922.92 |
| 02-0815-00 | Estopa | kg | 2.100000 | $28.97 | $60.84 |
| 02-0816-00 | Adelgazador thinner | lt | 15.000000 | $16.00 | $240.00 |
| 02-0817-00 | Primario Anticorrosivo | lt | 1.960000 | $67.00 | $131.32 |
| 02-0093-00 | Soldadura E-7018 | kg | 8.000000 | $46.33 | $370.64 |
| 02-0810-00 | Scotch lite grado ingenieria blanco | m2 | 1.056000 | $207.45 | $219.07 |
| 02-0821-00 | Bajo alfombra poli-pad | m2 | 0.600000 | $6.50 | $3.90 |
| 02-0820-00 | Papel Kraft | kg | 0.300000 | $9.00 | $2.70 |
| Suma de Material | $2,989.95 | ||||
| Mano de Obra | |||||
| 01-1007-20 | Cuadrilla No. 7: oficial especialista + ayudante >>Procesista >>Rend=0.9 pza/jor | jor | 1.100000 | $674.55 | $742.01 |
| 01-1002-162 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion >>Rend=1 pza/jor | jor | 1.000000 | $265.42 | $265.42 |
| 01-1035-08 | Operario especialista (soldador de primera) >>Rend=0.9 pza/jor | jor | 1.100100 | $445.73 | $490.35 |
| Suma de Mano de Obra | $1,497.77 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 03-0140-009 | Compresor de 375 pcm, 122 hpmod. xa 175 atlas copco (chicago pneumatic de 315 pcm 140 HP) >>PH=1.67 pza/hr | hora | 0.600000 | $169.44 | $101.66 |
| 03-0230-07 | Dobladora y cortadora de lamina y placa hasta 25mm de espesor Espamex PT 50-50 >>PH=1.25 pza/h | hora | 0.800000 | $157.72 | $126.18 |
| 03-0231-07 | Taladro electrico manual bosh mod. 1182 >>PH=2.6 pza/hr | hora | 0.380000 | $1.72 | $0.65 |
| 03-0180-10 | Soldadora Lincoln SAE 300 amp. K1277 mot. Perkins 4236, 4 cil., 60 HP, 1600 rpm, (sin operador). >>PH=1 pza/hr | hora | 1.000000 | $63.52 | $63.52 |
| 03-0214-10 | Camioneta Pick-Up Ford F-250 8 cilindros 1.5 ton. 85 HP >>PH=2 pza/h | hora | 0.500000 | $192.02 | $96.01 |
| Suma de Equipo | $388.02 | ||||
| Auxiliar | |||||
| 04-0711-08 | Perfil estructural rectangular P.T.R., kg incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. >>9.36m*4.54kg/m*1.03desp=43.7692kg | kg | 43.769200 | $11.32 | $495.47 |
| 02-0823-02 | Monten en canal 10" x 10" cal. 6 >>7.8m*4.25kg/m*1.03desp=34.1445 kg | kg | 34.144500 | $10.53 | $359.54 |
| 04-0153-02 | Placa de acero A-36; incluye valor de adquisicion carga + descarga + acarreo al 1er. km. y 49 kms. subsecuentes. >>Cartabones. 4pza*0.045m2/pza*99.59kg/m2* >>m2*1.03desp=18.4640 kg | kg | 18.464000 | $13.82 | $255.17 |
| 04-0157-14 | Lamina galvanizada cal. 16; incluye va- tor de adquisicion carga + descarga + acarreo al 1er km y 49kms. subsecuentes. >>11.9072m2*12.206kg/m2*1.03desp=149.7 kg | ton | 0.149700 | $16,873.03 | $2,525.89 |
| 04-0106-03 | Concreto f'c=200 kg/cm2 hecho in-situ agreg. max. 38mm producidos por el contratista. >>0.6m*0.6m*2*1.03desp=0.7416 m3 | m3 | 0.741600 | $1,167.55 | $865.86 |
| Suma de Auxiliar | $4,501.93 | ||||
| Costo Directo | $9,377.67 |