| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7171 | Senales informativas de recomendacion e informacion general. f) SIG-11 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0802-01 | Tornillo galvanizado de 3" x 1/8" | pza | 2.000000 | $9.60 | $19.20 |
| 02-0815-00 | Estopa | kg | 0.020000 | $28.97 | $0.58 |
| 02-0816-00 | Adelgazador thinner | lt | 0.200000 | $16.00 | $3.20 |
| 02-0817-00 | Primario Anticorrosivo | lt | 0.100000 | $67.00 | $6.70 |
| 02-0820-00 | Papel Kraft | kg | 0.020000 | $9.00 | $0.18 |
| 02-0821-00 | Bajo alfombra poli-pad | m2 | 0.050000 | $6.50 | $0.33 |
| 02-0093-00 | Soldadura E-7018 | kg | 0.060000 | $46.33 | $2.78 |
| 02-0810-04 | Scotch lite grado ingenieria negro | m2 | 0.120000 | $212.25 | $25.47 |
| 02-0810-00 | Scotch lite grado ingenieria blanco | m2 | 0.080000 | $207.45 | $16.60 |
| Suma de Material | $75.03 | ||||
| Mano de Obra | |||||
| 01-1007-26 | Cuadrilla No. 7: oficial especialista + ayudante >>Procesista >>Rend=9.92 pza/jor | jor | 0.100800 | $674.55 | $67.99 |
| 01-1002-176 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion >>Rend=9.92 pza/jor | jor | 0.100800 | $265.42 | $26.75 |
| 01-1035-14 | Operario especialista (soldador de primera) >>Rend=9.92 pza/jor | jor | 0.100800 | $445.73 | $44.93 |
| Suma de Mano de Obra | $139.68 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 03-0140-013 | Compresor de 375 pcm, 122 hpmod. xa 175 atlas copco (chicago pneumatic de 315 pcm 140 HP) >>PH=13.22 pza/h | hora | 0.075600 | $169.44 | $12.81 |
| 03-0230-12 | Dobladora y cortadora de lamina y placa hasta 25mm de espesor Espamex PT 50-50 >>PH=9.92 pza/h | hora | 0.100800 | $157.72 | $15.90 |
| 03-0231-12 | Taladro electrico manual bosh mod. 1182 >>PH=18.18 pza/h | hora | 0.048400 | $1.72 | $0.08 |
| 03-0180-15 | Soldadora Lincoln SAE 300 amp. mot. Perkins 4236, 4 cil., 60 HP, 1600 rpm, (sin operador). >>PH=1.65 pza/hr | hora | 0.120000 | $63.52 | $7.62 |
| 03-0214-15 | Camioneta Pick-Up Ford F-250 8 cilindros 1.5 ton. 85 hp >>PH=20.66 pza/hr | hora | 0.048400 | $192.02 | $9.29 |
| Suma de Equipo | $45.71 | ||||
| Auxiliar | |||||
| 04-0157-20 | Lamina galvanizada cal. 16; incluye va- lor de adquisicion carga + descarga + acarreo al 1er km y 49kms. subsecuentes. >>0.1220 m2*12.206 kg/m2*1.03 desp=1.5338kg | ton | 0.001500 | $16,873.03 | $25.31 |
| 04-0711-02 | Perfil estructural rectangular P.T.R., incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. >>2m*4.54 kg/m*1.03desp=9.3524kg | kg | 9.352400 | $11.32 | $105.87 |
| 04-0160-00 | Excavaciónes para estructuras, de acuerdo con su clasificación, a cualquier profundidad. Inciso (3.02.02.022-H.01): a) Excavado a mano, en seco: 1) En material "B" | m3 | 0.080000 | $126.65 | $10.13 |
| 04-0106-00 | Concreto f'c = 200 kg/cm² hecho in-situ agreg. max. 38mm producidos por el contratista. | m3 | 0.080000 | $1,167.55 | $93.40 |
| Suma de Auxiliar | $234.71 | ||||
| Costo Directo | $495.13 |