| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7144 | Señales de alineamiento vertical: Fantasmos metalicos. | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0811-00 | Cloruro de polivinil de alto impacto >>0. 107m*1.2m*1.03desp=0.1323m2/pza | m2 | 0.132300 | $348.28 | $46.08 |
| 02-0812-00 | Tubo perno de 15cm de largo x 2 de diam. | pza | 1.000000 | $18.40 | $18.40 |
| 02-0810-00 | Scotch lite grado ingenieria blanco | m2 | 0.132300 | $207.45 | $27.45 |
| 02-0810-01 | Scotch lite grado ingenieria rojo >>0.04m*0.15m*1.03desp=0.0062m2/pza | m2 | 0.006200 | $215.18 | $1.33 |
| 02-0810-02 | Scotch lite grado ingenieria negro >>0.107m*01m*1.03 desp=0.011 m2/pza | m2 | 0.011000 | $212.25 | $2.33 |
| Suma de Material | $95.59 | ||||
| Mano de Obra | |||||
| 01-1002-171 | Cuadrilla No. 2: peon + 1/10 cabo >>Extraccion y demolicion >>Rend=8 pza/jor | jor | 0.125000 | $265.42 | $33.18 |
| 01-1002-172 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion >>Ren.d=7 pza/jor | jor | 0.142900 | $273.38 | $39.07 |
| Suma de Mano de Obra | $72.24 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| 04-0104-01 | Concreto f'c=100 kg/cm2 hecho in-situ agreg. max. 38mm producidos por el contratista. >>0.3m*0.15rn*0.15m*1.03desp=0.007m3/pza | m3 | 0.007000 | $997.37 | $6.98 |
| Suma de Auxiliar | $6.98 | ||||
| Costo Directo | $174.82 |