| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7170 | Senales informativas de recomendacion e informacion general. e) SIG-10 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0093-00 | Soldadura E-7018 | kg | 0.660000 | $46.33 | $30.58 |
| 02-0817-00 | Primario Anticorrosivo | lt | 0.200000 | $67.00 | $13.40 |
| 02-0815-00 | Estopa | kg | 0.116700 | $28.97 | $3.38 |
| 02-0820-00 | Papel Kraft | kg | 0.030000 | $9.00 | $0.27 |
| 02-0823-00 | Monten en canal 6" x 6" cal. 6 kg >>4m*25.5kg/m*1.03desp=105.06kg | kg | 105.060000 | $10.53 | $1,106.28 |
| 02-0810-00 | Scotch lite grado ingenieria blanco | m2 | 0.320000 | $207.45 | $66.38 |
| 02-0821-00 | Bajo alfombra poli-pad | m2 | 0.070000 | $6.50 | $0.46 |
| 02-0816-00 | Adelgazador thinner | lt | 0.800000 | $16.00 | $12.80 |
| 02-0085-01 | Pernos de anclaje de 1 1/2" diam. x 160 cm | pza | 6.000000 | $96.55 | $579.30 |
| Suma de Material | $1,812.85 | ||||
| Mano de Obra | |||||
| 01-1007-25 | Cuadrilla No. 7: oficial especialista + ayudante >>Procesista >>Rend=3.31 pza/jor | jor | 0.302500 | $674.55 | $204.05 |
| 01-1002-175 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion >>Rend=1.65 pza/jor | jor | 0.605000 | $265.42 | $160.58 |
| 01-1035-13 | Operario especialista (soldador de primera) >>Rend=3.31 pza/jor | jor | 0.302500 | $445.73 | $134.83 |
| Suma de Mano de Obra | $499.46 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 03-0140-012 | Compresor de 375 pcm, 122 hpmod. xa 175 atlas copco (chicago pneumatic de 315 pcm 140 HP) >>PH=1.65 pza/hr | hora | 0.605000 | $169.44 | $102.51 |
| 03-0230-11 | Dobladora y cortadora de lamina y placa hasta 25mm de espesor Espamex PT 50-50 >>PH=2.48 pza/hr | hora | 0.403300 | $157.72 | $63.61 |
| 03-0231-11 | Taladro electrico manual bosh mod. 1182 >>PH=4.13 pza/hr | hora | 0.242000 | $1.72 | $0.42 |
| 03-0180-14 | Soldadora Lincoln SAE 300 amp. K1277 mot. Perkins 4236, 4 cil., 60 HP, 1600 rpm, (sin operador). >>PH=3.31 pza/hr | hora | 0.302500 | $63.52 | $19.21 |
| 03-0214-14 | Camioneta Pick-Up Ford F-250 8 cilindros 1.5 ton. 85 hp >>PH=4.96 pza/hr | hora | 0.201700 | $192.02 | $38.73 |
| Suma de Equipo | $224.48 | ||||
| Auxiliar | |||||
| 04-0711-04 | Perfil estructural rectangular P.T.R., incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. >>5.28m*4.54 kg/m*1.03desp=24.6903 kg | kg | 24.690300 | $11.32 | $279.49 |
| 04-0106-00 | Concreto f'c = 200 kg/cm² hecho in-situ agreg. max. 38mm producidos por el contratista. | m3 | 0.329600 | $1,167.55 | $384.82 |
| 04-0153-00 | Placa de acero A-36; incluye valor de adquisición carga + descarga + acarreo al 1er. km. y 49 kms. subsecuentes. | kg | 23.900000 | $13.82 | $330.30 |
| 04-0157-19 | Lamina galvanizada cal. 16; incluye va- lor de adquisicion carga + descarga + acarreo al 1er km y 49kms. subsecuentes. >>1.6969m2*12.206kg/m2*1.03desp=21.3337kg | ton | 0.021300 | $16,873.03 | $359.40 |
| Suma de Auxiliar | $1,354.01 | ||||
| Costo Directo | $3,890.81 |