| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1340 | Defensa metalica | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0806-00 | Defensa metal galvanizado cal. 12. >>Para un tramo de 3.81m | m | 7.620000 | $660.00 | $5,029.20 |
| 02-0800-00 | Separador galvanizado cal. 12. | pza | 2.000000 | $19.00 | $38.00 |
| 02-0801-00 | Terminal galvanizada cal. 10. | pza | 1.000000 | $168.78 | $168.78 |
| 02-0802-00 | Tornillo galvanizado 5/8" x 1 1/4" | pza | 8.000000 | $7.10 | $56.80 |
| 02-0802-00 | Tornillo galvanizado 5/8" x 1 1/4" | pza | 2.000000 | $7.10 | $14.20 |
| Suma de Material | $5,306.98 | ||||
| Mano de Obra | |||||
| 01-1002-148 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion >>Rend=3 pza/jor | jor | 0.333300 | $265.42 | $88.46 |
| Suma de Mano de Obra | $88.46 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| 04-0160-00 | Excavaciónes para estructuras, de acuerdo con su clasificación, a cualquier profundidad. Inciso (3.02.02.022-H.01): a) Excavado a mano, en seco: 1) En material "B" | m3 | 0.007200 | $126.65 | $0.91 |
| 04-0711-00 | Perfil estructural rectangular P.T.R., incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. >>0.92m*6.47kg/m*1.03desp*2=12.2619kg | kg | 12.261900 | $11.32 | $138.80 |
| Suma de Auxiliar | $139.72 | ||||
| Costo Directo | $5,535.16 |