| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7162 | Señales informativas de destino. e) SID-12 | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 02-0824-00 | Placa de acero de 3/4" >>0.5m*0.5m*149.38kg/m2*1.03desp*2=76.93kg | kg | 76.930700 | $13.50 | $1,038.56 |
| 02-0825-00 | Birlo de 1" diam. 12" prof. galv. | pza | 12.000000 | $76.91 | $922.92 |
| 02-0815-00 | Estopa | kg | 2.100000 | $28.97 | $60.84 |
| 02-0816-00 | Adelgazador thinner | lt | 15.000000 | $16.00 | $240.00 |
| 02-0817-00 | Primario Anticorrosivo | lt | 1.960000 | $67.00 | $131.32 |
| 02-0093-00 | Soldadura E-7018 | kg | 8.000000 | $46.33 | $370.64 |
| 02-0810-00 | Scotch lite grado ingenieria blanco | m2 | 1.056000 | $207.45 | $219.07 |
| 02-0821-00 | Bajo alfombra poli-pad | m2 | 0.600000 | $6.50 | $3.90 |
| 02-0820-00 | Papel Kraft | kg | 0.300000 | $9.00 | $2.70 |
| Suma de Material | $2,989.95 | ||||
| Mano de Obra | |||||
| 01-1007-24 | Cuadrilla No. 7: oficial especialista + ayudante >>Procesista | jor | 1.344400 | $674.55 | $906.87 |
| 01-1002-174 | Cuadrilla No. 2: peon + 1/10 cabo >>Colocacion | jor | 1.200000 | $265.42 | $318.50 |
| 01-1035-12 | Operario especialista (soldador de primera) | jor | 1.344400 | $445.73 | $599.24 |
| Suma de Mano de Obra | $1,824.61 | ||||
| Herramienta | |||||
| 00-0000-00 | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| 03-0140-000 | Compresor de 375 pcm, 122 hpmod. xa 175 atlas copco (chicago pneumatic de 315 pcm 140 HP) | hora | 0.724600 | $169.44 | $122.78 |
| 03-0230-00 | Dobladora y cortadora de lamina y placa hasta 25mm de espesor Espamex PT 50-50 | hora | 0.968000 | $157.72 | $152.67 |
| 03-0231-01 | Taladro electrico manual bosh mod. 1182 | hora | 0.465400 | $1.72 | $0.80 |
| 03-0180-00 | Soldadora Lincoln SAE 300 amp. K1277 mot. Perkins 4236, 4 cil., 60 HP, 1600 rpm., (sin operador). | hora | 1.200000 | $63.52 | $76.22 |
| 03-0214-00 | Camioneta Pick-Up Ford F-250 8 cilindros 1.5 ton. 85 HP | hora | 0.605000 | $192.02 | $116.17 |
| Suma de Equipo | $468.65 | ||||
| Auxiliar | |||||
| 04-0711-08 | Perfil estructural rectangular P.T.R., kg incluye valor de adquisicion, carga + descarga + acarreo al 1er. km y 9 kms. subsecuentes. >>9.36m*4.54kg/m*1.03desp=43.7692kg | kg | 43.769200 | $11.32 | $495.47 |
| 02-0823-02 | Monten en canal 10" x 10" cal. 6 >>7.8m*4.25kg/m*1.03desp=34.1445 kg | kg | 34.144500 | $10.53 | $359.54 |
| 04-0153-02 | Placa de acero A-36; incluye valor de adquisicion carga + descarga + acarreo al 1er. km. y 49 kms. subsecuentes. >>Cartabones. 4pza*0.045m2/pza*99.59kg/m2* >>m2*1.03desp=18.4640 kg | kg | 18.464000 | $13.82 | $255.17 |
| 04-0157-14 | Lamina galvanizada cal. 16; incluye va- tor de adquisicion carga + descarga + acarreo al 1er km y 49kms. subsecuentes. >>11.9072m2*12.206kg/m2*1.03desp=149.7 kg | ton | 0.149700 | $16,873.03 | $2,525.89 |
| 04-0106-00 | Concreto f'c = 200 kg/cm² hecho in-situ agreg. max. 38mm producidos por el contratista. | m3 | 0.741600 | $1,167.55 | $865.86 |
| Suma de Auxiliar | $4,501.93 | ||||
| Costo Directo | $9,785.13 |