| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1 | TRAZO Y NIVELACIÓN | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0300-60 | CALHIDRA EN SACO | TON | 0.000030 | $1,200.00 | $0.04 |
| 1501-45 | CARRETE DE HILO DE PLASTICO PARA TRAZO CALIBRE 10 | ROL | 0.000600 | $14.30 | $0.01 |
| 1900-10 | MADERA DE PINO DE 2A. EN BARROTE DE 2" X 4" | PT | 0.001300 | $12.00 | $0.02 |
| Suma de Material | $0.06 | ||||
| Mano de Obra | |||||
| MOTOP | CUADRILLA (1 AUXILIAR DE TOP. + 1 CADENERO) | JOR | 0.001260 | $913.44 | $1.15 |
| 02-0019 | CUADRILLA (1 PEON) | JOR | 0.000960 | $413.15 | $0.40 |
| Suma de Mano de Obra | $1.55 | ||||
| Equipo | |||||
| 03-4390 | CAMION PICK-UP FORD 1.5 TONELADAS MOTOR DE GASOLINA | Hora | 0.019400 | $59.41 | $1.15 |
| 03-4280 | NIVEL PARA MEDICION K-E, TIPO DUMPY, MODELO 503 | Hora | 0.023580 | $0.83 | $0.02 |
| 03-4290 | ESTACION TOTAL SOKKIA SET-610 | Hora | 0.004690 | $18.28 | $0.09 |
| Suma de Equipo | $1.26 | ||||
| Costo Directo | $2.87 |