| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-14 | SUMINISTRO Y COLOCACION DE VIGA IPR DE 10" X 5 3/4", INCLUYE: PLACA, SOLDADURA, PRIMER, PINTURA ESMALTE, MATERIAL MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ESTRUCTURA-05 | VIGA IPR DE 10" X 5 3/4" | KG | 1.020000 | $10.50 | $10.71 |
| ESMALTE-01 | PRIMARO ANTICORROSIVO SHERWIN WILIANS LINE KEM KROMIC DE 3 MM | LT | 0.050000 | $52.00 | $2.60 |
| ESMALTE-03 | SOLVENTE | LT | 0.020000 | $18.00 | $0.36 |
| ESMALTE-04 | LIJA DE ESMERIL | PLIEGO | 0.020000 | $9.00 | $0.18 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.020000 | $4.05 | $0.08 |
| COMBUSTIBLE | OXIGENO | M3 | 0.020000 | $29.00 | $0.58 |
| ESTRUCTURA-03 | SOLDADURA 70/18 | KG | 0.090000 | $31.00 | $2.79 |
| Suma de Material | $17.30 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | JOR | 0.002000 | $803.02 | $1.61 |
| CUADRILLA NO. 42 | (1 Pailero + 1 Soldador + 2 ayudantes A). | Jor | 0.006000 | $1,448.13 | $8.69 |
| Suma de Mano de Obra | $10.29 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 | |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| COMPRESOR | EQUIPO PARA APLICAR PINTURA EN FRANJAS (PINTA RAYAS) | HR | 0.002000 | $147.42 | $0.29 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.001000 | $0.13 | $0.00 |
| ESMERILADORA | ESMERILADORA | HR | 0.003000 | $5.98 | $0.02 |
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.004000 | $35.34 | $0.14 |
| Suma de Equipo | $0.45 | ||||
| Costo Directo | $28.05 |