| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-01 | FIRME DE CONCRETO DE F'C=200 KG/CM2. R.N. A.M. 3/4" ARMADO CON MALLA ELECTROSOLDAD 6X6-6/6, INCLUYE: MATERIAL, MANO DE OBRA Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-MALL-01 | MALLA ELECTROSOLDAD 6X6-6/6 | M2 | 1.100000 | $10.00 | $11.00 |
| Suma de Material | $11.00 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.060000 | $571.26 | $34.28 |
| Suma de Mano de Obra | $34.28 | ||||
| Auxiliar | |||||
| CONCRETO F-C= 200 KG | CONCRETO DE F'C=200 KG/CM2 | M3 | 0.051500 | $765.04 | $39.40 |
| Suma de Auxiliar | $39.40 | ||||
| Costo Directo | $84.68 |