| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-15 | SUMINISTRO Y COLOCACION DE POSTE PM-1, INCLUYE: CARTABONES, SOLDADURA, PRIMER, PINTURA ESMALTE, COLOR DURANODICK FORRADO CON DUELA Y ANGULO DE ALUMINIO DURANODICK, MATERIAL, MANO DE OBRA Y HERRAMIENTA. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ESTRUCTURA-04 | PLACA DE ACERO A-36 DE /4 Y DE 3/4" | KG | 44.000000 | $10.92 | $480.48 |
| ESMALTE-01 | PRIMARO ANTICORROSIVO SHERWIN WILIANS LINE KEM KROMIC DE 3 MM | LT | 0.050000 | $52.00 | $2.60 |
| ESMALTE-03 | SOLVENTE | LT | 0.020000 | $18.00 | $0.36 |
| ESMALTE-04 | LIJA DE ESMERIL | PLIEGO | 0.020000 | $9.00 | $0.18 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.020000 | $4.05 | $0.08 |
| COMBUSTIBLE | OXIGENO | M3 | 0.020000 | $29.00 | $0.58 |
| ESTRUCTURA-03 | SOLDADURA 70/18 | KG | 0.090000 | $31.00 | $2.79 |
| Suma de Material | $487.07 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | JOR | 0.100000 | $805.53 | $80.55 |
| CUADRILLA NO. 42 | (1 Pailero + 1 Soldador + 2 ayudantes A). | Jor | 0.200000 | $1,436.38 | $287.28 |
| Suma de Mano de Obra | $367.83 | ||||
| Equipo | |||||
| COMPRESOR | EQUIPO PARA APLICAR PINTURA EN FRANJAS (PINTA RAYAS) | HR | 0.002000 | $101.17 | $0.20 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.001000 | $0.13 | $0.00 |
| ESMERILADORA | ESMERILADORA | HR | 0.003000 | $5.98 | $0.02 |
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 0.004000 | $35.34 | $0.14 |
| Suma de Equipo | $0.36 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO METALICO | DIA | 1.000000 | $30.69 | $30.69 |
| Suma de Auxiliar | $30.69 | ||||
| Costo Directo | $885.95 |