| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-13 | ACERO DE REFUERZO DEL No. 8, 1" F'Y=4200 KG/CM2. EN ESTRUCTURA, INCLUYE: SUMINISTRO, HABILITADO, ARMADO, TRASLAPES, GANCHOS, ANCLAJES, SILLETAS, SEPARADORES, ALAMBRE, HERRAMIENTA, MANO DE OBRA Y TRABAJOS NECESARIOS. | TON |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-8 | ACERO DE REFUERZO DEL No. 8, 1" F'Y=4200 KG/CM2. | TON | 1.190000 | $9,500.00 | $11,305.00 |
| ACERO-18 | ALAMBRE RECOCIDO | KG-- | 12.500000 | $12.17 | $152.13 |
| Suma de Material | $11,457.13 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | JOR | 5.000000 | $568.08 | $2,840.40 |
| Suma de Mano de Obra | $2,840.40 | ||||
| Costo Directo | $14,297.53 |