| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OE-07 | GUARNICIÓN DE CONCRETO PREMEZCLADO F'C=250 KG/CM2. DE FORMA TRAPEZOIDAL DE 15 X 20 X 40 CMS., INCLUYE: TRAZO, EXCAVACIÓN, AFINE, CIMBRA, DESCIMBRA, AFINE, VOLTEADOR, RELLENO, MATERIALES DE CONSUMO Y TRABAJOS NECESARIOS. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA-01 | CIMBRAPLAY 16 MM | M2** | 0.300000 | $80.62 | $24.19 |
| CIMBRA-02 | CLAVO | Kg.-- | 0.250000 | $13.54 | $3.39 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.050000 | $4.68 | $0.23 |
| Suma de Material | $27.81 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.050000 | $1,657.18 | $82.86 |
| Suma de Mano de Obra | $82.86 | ||||
| Auxiliar | |||||
| CONCRETO F-C= 250 KG | CONCRETO DE F'C=250 KG/C M2 | M3 | 0.070000 | $826.46 | $57.85 |
| Suma de Auxiliar | $57.85 | ||||
| Costo Directo | $168.52 |