| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-08 | CADENA INTERMEDIA DE 15X 15 CM., INCLUYE CIMBRA Y DESCIMBRA, CONCRETO HECHO EN OBRA F'C=250 KG/CM2-3/4", REFORZADA CON 4 VARILLAS A.R. DE 3/8" ESTRIBOS DE 1/4" A/C 20 CM., INCLUYE: CIMBRA DE MADERA DE PINO DE 2a, CIMBRADO, DESCIMBRADO, ANCLAJES, ACARREOS, SUMINISTRO DE MATERIALES DE CONSUMO Y TRABAJOS NECESARIOS. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-3/8" | ACERO DE 3/8" | TON | 0.002300 | $9,500.00 | $21.85 |
| ACERO-18 | ALAMBRE RECOCIDO | KG-- | 0.200000 | $12.17 | $2.43 |
| ACERO-1/4 | ALAMBRON DE 1/4 | KG | 0.946000 | $10.49 | $9.92 |
| CIMBRA-01 | CIMBRAPLAY 16 MM | M2** | 0.100000 | $80.62 | $8.06 |
| CIMBRA-04 | MADERA DE PINO | PT-- | 1.000000 | $5.60 | $5.60 |
| CIMBRA-02 | CLAVO | Kg.-- | 0.150000 | $13.54 | $2.03 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.600000 | $4.68 | $2.81 |
| Suma de Material | $52.71 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.097500 | $571.26 | $55.70 |
| Suma de Mano de Obra | $55.70 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO METALICO | DIA | 0.097500 | $28.26 | $2.76 |
| CONCRETO F-C= 250 KG | CONCRETO DE F'C=250 KG/C M2 | M3 | 0.024700 | $823.06 | $20.33 |
| Suma de Auxiliar | $23.08 | ||||
| Costo Directo | $131.49 |