| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OE-01 | ADECUACION DE BARDA AL NUEVO DISEÑO, INCLUYE: DEMOLICION DE MUROS, EMBOQUILLADOS, REMATES, INCLUYE: MATERIAL, MANO DE OBRA Y HERRAMINTA. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-3/8" | ACERO DE 3/8" | TON | 0.006300 | $9,500.00 | $59.85 |
| AGREGADO-021 | TABIQUE ROJO | PZA-- | 60.000000 | $1.04 | $62.40 |
| ACERO-18 | ALAMBRE RECOCIDO | KG-- | 0.200000 | $12.17 | $2.43 |
| ACERO-1/4 | ALAMBRON DE 1/4 | KG | 0.946000 | $10.49 | $9.92 |
| CIMBRA-01 | CIMBRAPLAY 16 MM | M2** | 0.200000 | $80.62 | $16.12 |
| CIMBRA-04 | MADERA DE PINO | PT-- | 1.000000 | $5.60 | $5.60 |
| CIMBRA-02 | CLAVO | Kg.-- | 0.150000 | $13.54 | $2.03 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.600000 | $4.68 | $2.81 |
| Suma de Material | $161.17 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 1.000000 | $668.45 | $668.45 |
| Suma de Mano de Obra | $668.45 | ||||
| Auxiliar | |||||
| MORTERO-1:4 | MORTERO CEMENTO ARENA 1:4 | m3 | 0.040000 | $636.99 | $25.48 |
| ANDAMIO | ANDAMIO METALICO | DIA | 0.097500 | $30.69 | $2.99 |
| CONCRETO F-C= 250 KG | CONCRETO DE F'C=250 KG/C M2 | M3 | 0.030000 | $826.46 | $24.79 |
| Suma de Auxiliar | $53.27 | ||||
| Costo Directo | $882.89 |