| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OI74.- | SUMINISTRO Y COLOCACION DE SISTEMA DE TIERRA PARA LA SUBESTACION CON CABLE DESNUDO CAL 4/0 MCM 14 VARILLAS COOPERWERD 5/8 X 3.00 ML Y CONECTORES GAR CAL 4/0 ASI COMO EL USO DE SOLDADURA TIPO X MARCA CARDWELD ASI COMO TYODO LO NECESARIO PARA SU CORRECTA EJECUCION | SIST |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CABLE THWN CAL. 4/0 | CABLE THWN CAL. 4/0 | ML | 87.000000 | $76.30 | $6,638.10 |
| VARILLA COPERWELD | VARILLA COPERWELD DE 5/8" DE DIÁMETRO, 305 CM DE LONGITUD. MARCA BURND | PZA | 14.000000 | $147.00 | $2,058.00 |
| CONECTOR GAR CAL 4/0 | PZA | 14.000000 | $225.00 | $3,150.00 | |
| MOLDE CAD. 4/0 | PZA | 0.200000 | $2,458.00 | $491.60 | |
| SOLD CARDW. 150 | PZA | 6.000000 | $185.00 | $1,110.00 | |
| TUBO ALBAÑAL 10" | PZA | 14.000000 | $358.00 | $5,012.00 | |
| TAPA 10" DIAM. | PZA | 14.000000 | $125.00 | $1,750.00 | |
| ZAPATA T/ Z CAL 4/0 | PZA | 1.000000 | $148.00 | $148.00 | |
| TUBO C.PVC TP 38 MM | TUBO C.PVC TP 38 MM | ML | 32.000000 | $13.86 | $443.52 |
| CONCRETO PREME-04 | CONCRETO PREMEZCLADO F'C=300KG/CM2 CON CEMENTO TIPO CPO CON UNA RELACION AGUA-CEMENTO DE 0.55 BOMBEADO | M3 | 9.600000 | $1,000.00 | $9,600.00 |
| ACERO 07 | ARMEX 12-2 | ML | 48.000000 | $18.00 | $864.00 |
| Suma de Material | $31,265.22 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | Jor | 9.000000 | $874.53 | $7,870.77 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 3.200000 | $1,718.79 | $5,500.13 |
| Suma de Mano de Obra | $13,370.90 | ||||
| Equipo | |||||
| MAQUINARIA-11 | ESCAVADORA SOBRE ORUGA MODELO 330 CL CON MOTOR DIESEL C9 ATAAC DE 247 H.P.AL VOLANTE A 1800 R.P.M. | HR | 3.500000 | $1,017.57 | $3,561.50 |
| Suma de Equipo | $3,561.50 | ||||
| Costo Directo | $48,197.61 |