| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OI01.- | SUMINISTRO E INSTALACION DE SUBESTACION DE 75 KVA PARA ALIMENTAR A LOCALES COMERCIALES, INCLUYE TRANSFORMADOR ,INTERRUPTOR PRICIPAL ,ALIMENTADOR PRINCIPAL,HERRAJES DE POSTE Y ACCESORIOS, ASI COMO TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRANSFORMADOR 75 KVA | TRANSFORMADOR DE 75 KVA MCA. PROLEC OPERACION RADIAL NORMA J. REL. DE OPERACION DE 13200/ 220- 127 V.TIPO PEDESTAL. | PZA | 1.000000 | $76,369.00 | $76,369.00 |
| CABLE XLP CAL. 1/0 | CON ARBORESENCIA | ML | 120.000000 | $53.00 | $6,360.00 |
| TERMINAL TERMOCONTRA | CAL 1/0 | PZA | 3.000000 | $1,006.99 | $3,020.97 |
| APARTARRAYO DE 27KV | OXIDO DE ZINC | PZA | 3.000000 | $790.00 | $2,370.00 |
| CORTA CIRCUITO 27 KV | PZA | 3.000000 | $643.40 | $1,930.20 | |
| LISTON FUSIBLE 13 A. | PZA | 3.000000 | $150.00 | $450.00 | |
| CONECTOR PERICO CAL2 | PZA | 3.000000 | $73.00 | $219.00 | |
| CONECTOR ESTRIBO 2 | PZA | 3.000000 | $85.00 | $255.00 | |
| CABLE THW CAL 10 | ML | 45.000000 | $3.50 | $157.50 | |
| CON.TABACO CAL 10 | PZA | 3.000000 | $6.00 | $18.00 | |
| CODO PREMOL. CAL 1/0 | PZA | 3.000000 | $649.99 | $1,949.97 | |
| ADAPTADOR CAL 1/0 | PZA | 3.000000 | $343.00 | $1,029.00 | |
| INSERTO CAL 1/0 | PZA | 3.000000 | $515.00 | $1,545.00 | |
| ZAPATA BURDY CAL 1/0 | DOBLE OJILLO | PZA | 3.000000 | $85.00 | $255.00 |
| CABLE DES. CAL 2 | ML | 50.000000 | $26.30 | $1,315.00 | |
| ZAPATAS BURDY 4/0 | PZA | 4.000000 | $106.00 | $424.00 | |
| CABLE THW 4/0 | ML | 40.000000 | $79.46 | $3,178.40 | |
| GABINETE KAL | PZA | 1.000000 | $1,450.00 | $1,450.00 | |
| INTER. KAL 36225 | PZA | 1.000000 | $6,333.81 | $6,333.81 | |
| VARILLA D TIERRA 5/8 | CON PROTOCOLO | PZA | 2.000000 | $145.00 | $290.00 |
| CONCHA PONCHABLE C.2 | PZA | 2.000000 | $45.00 | $90.00 | |
| CINTA DE AISL. 23 | PZA | 1.000000 | $58.00 | $58.00 | |
| Suma de Material | $109,067.85 | ||||
| Mano de Obra | |||||
| CUADRILLA ALTA TENS. | Cuadrilla Electrica Alta Tension | jor | 15.000000 | $2,165.40 | $32,481.00 |
| Suma de Mano de Obra | $32,481.00 | ||||
| Equipo | |||||
| GRUA HIAB | Grua Tipo Hiab de 3.5 ton.Montada en camion de 10 ton | HR | 2.000000 | $312.00 | $624.00 |
| Suma de Equipo | $624.00 | ||||
| Costo Directo | $142,172.85 |