| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| OI21.- | ACONDICIONAMIENTO DE LA ALIMENTACION PRINCIPAL HIDRAULICA DE 3/4" PARA LENADO DE CISTERNA QUE SE OCULTARA POR LA PARTE DE AFUERA DONDE SE FORRO DE AZULEJOS | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOLDADURA 50X50 | SOLDADURA 50X50 | PZA | 0.650000 | $35.00 | $22.75 |
| PASTA P/SOLDAR | PASTA P/SOLDAR | PZA | 1.300000 | $30.59 | $39.77 |
| ESTOPA | ESTOPA | KG | 0.850000 | $13.20 | $11.22 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.041670 | $6.00 | $0.25 |
| MATER. MISCELANEOS | MATER. MISCELANEOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Material | $73.99 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 2.500000 | $857.88 | $2,144.70 |
| Suma de Mano de Obra | $2,144.70 | ||||
| Costo Directo | $2,218.69 |